How much concrete do I need?

Enter your slab or footing dimensions to get the cubic yards and the number of 60lb and 80lb bags — with 10% waste built in.

ft

Length of the slab or footing.

ft

Width of the slab or footing.

in

Slab depth — 4 inches is typical for a residential slab.

×

Number of identical slabs or footings.

You'll need about

1.36

cubic yards (with 10% waste)

1.23

yds³ exact

56

80lb bags

75

60lb bags

33.33 cubic feet total

Bidding this job? Turn your takeoff into a priced quote your customer can approve — build a free estimate, then let Hero365 send it and win the work.

Get the next tool first

New free calculators and one short weekly tip for running a trades business — no spam, unsubscribe anytime.

How this is calculated

length (ft) × width (ft) × (thickness in ÷ 12) = cubic feet
cubic feet ÷ 27 = cubic yards
cubic yards × 1.10 = yards to order (with waste)

Bag counts assume about 0.6 ft³ per 80lb bag and 0.45 ft³ per 60lb bag (manufacturer averages). For pours larger than about a cubic yard, ready-mix delivery is usually more economical than bags. This is a planning estimate — confirm with your ready-mix supplier before ordering.

Concrete: FAQ

How much concrete do I need?

Multiply length × width × thickness to get the volume, then convert to cubic yards (divide cubic feet by 27). For example, a 10 ft × 10 ft slab at 4 inches thick is about 1.23 cubic yards — roughly 1.36 yards once you add 10% for waste. This calculator does the math from your own dimensions.

How do you calculate cubic yards of concrete?

Cubic yards = (length in feet × width in feet × thickness in feet) ÷ 27. Convert thickness from inches to feet by dividing by 12. Always order a little extra — about 10% — to cover spillage, uneven subgrade, and over-excavation.

How many bags of concrete are in a cubic yard?

A cubic yard is 27 cubic feet. An 80lb bag of pre-mixed concrete yields about 0.6 cubic feet, so a cubic yard takes roughly 45 bags; a 60lb bag yields about 0.45 cubic feet, or about 60 bags per yard. Bags are practical for small pours — for anything over about a cubic yard, ready-mix delivery is usually cheaper.

How much extra concrete should I order for waste?

Add about 10%. Subgrade is rarely perfectly level, forms flex, and some concrete is always lost to spillage — running short mid-pour is far more expensive than ordering a little extra. This calculator adds 10% to the “with waste” figure automatically.